Pipeline Rehabilitation Phase IV

24 Apr

Scope of work:

⦁ This is a major pipeline replacement and reconditioning project for upgrading and rehabilitation of the existing 48”, QA-7/ QRT-9, 16” BRT-1 and 40”/42” BRT-2, QA-5 (42”), QA-6 (42”), QRT-8 (42”), QRT-7 (42”) pipelines. A brief summary of the quantities of each category of works involvement in this project is listed below:

⦁ Total 42” Pipeline Replacement – 150 KM

⦁ Total 48” Pipeline Replacement – 65 KM

⦁ Total Recondition Length – 30 KM / Thrust boring, 42” / 48” – 20 EA

⦁ Row & Sabkah Pad Construction – 2,300,000M3

⦁ 42” / 48” MOV’s Replacement Including J.O.

⦁ Modifications – 30 EA

⦁ Abandoned/Replaced Pipes Removal – 25000 Tons

⦁ 2-Km of pipe replacement in world’s largest Rastanura Refinery which was on the ring guider.

Project Details:

Type of Project : LSPB

Location : Qatif

Duration : 2005 to 2006